Installation Instructions

1) Sweep floor, and remove any protrusions from the floor surface, make sure floor is dry.  A levelling screed may be used where required to level floor surface or In minor cases of unevenness sand may be used. Wood blocks may be used to provide support for basins, Bidets and WC pans etc.

2) Fix manifold(s) in position(s) shown on layout drawing using installation kit provided making due allowance for connecting pipes and any other equipment to be Installed adjacent to the manifold.  Manifolds should be installed at approximately 600mm up from the subfloor or as required.

3) Run edge insulation strip around room perimeter, overlapping at joins.

4) Cut and fit insulation until floor area is completely covered.

5) Lay polyethylene building film on top of the insulation, making sure that film extends up the walls by 200mm and that the film overlaps at joints by approximately 100mm. (Joints do not need to be sealed).  Pay attention to expansion joint positions shown on drawing or agreed with architect.

6) Lay grid on top of insulation making sure that grid legs' face down, using grid binders.  Wire grid edges together,(4 binding wires per grid). Cut grid where required.  Grid should overlap by 100mm.  Grid should stop just short of the edge Insulation strip and also should be carried under cupboards etc, even though there may be no heating pipes.

PLEASE OBSERVE SAFETY PRECAUTIONS WHEN HANDLING AND CUTTING GRID

7) Arrange and fix clips according to pipe spacing shown on layout drawing, with one clip to every 0.5 metre of pipe run and two at bends.  When not shown at a different spacing, connecting pipe 'tails' from the manifold to the heating circuit should be spaced at 100mm between flow and return.

8) Starting at the appropriate heating circuit at the manifold, connect pipe to flow and then clip pipe to grid according to layout drawing and previously laid pipe clips.  Velta PEX 151 pipe is marked at 1 metre Intervals to enable the correct length of pipe for the heating circuit to be easily measured off.  The beginning metre mark will probably not start at one as the markings actually indicate the length of pipe within a manufactured batch.  For example: If the start mark is 2345 and 100 metres of pipe is required then the pipe should be cut off at 2445.  Pipe must be laid in the 'snail' pattern as detailed previously unless shown otherwise.
There will be no pipe joints in the floor unless previously agreed.
If, at any time the pipe is accidentally kinked it may be restored to the proper shape without damage by gently applying hot air from a heat gun until the plastic 'remembers' its correct shape.
When back at manifold cut pipe to length and connect pipe to appropriate return connection on manifold.  When all heating circuits have been completed; make sure
manifold connections are tight.

9) Connect hose to manifold flow connection on the left hand side of the manifold.  Connect other end of hose to a suitable mains water supply.  Connect another hose to the manifold return connection on the right hand side of the manifold.  Other end of hose should be taken to a suitable drain point.
Make sure all heating circuits are shut down.  White control valves on the lower half of the manifold should be turned CLOCKWISE as should the white valve covers on the top half of the manifold.  Turn on water supply to the manifold.

10) Starting at the left-most heating circuit open the control valve slowly anticlockwise until water flows into the heating pipe.  Continue opening until valve is fully open (3.5 turns).  Slowly open appropriate white valve cover anticlockwise.  Water will now flow through the circuit and out of the drain hosepipe taking any air with it.  When all air has been expelled from the heating circuit close off both knobs and repeat for the next heating circuit, until all heating circuits have been filled.

11) Turn off water supply and remove hosepipes.  Blank off manifold return outlet (1" bsp female connection on right hand side of manifold).  Attach Test pressure pump to manifold flow socket (1" bsp female connection on left hand side of manifold).  Open all heating circuit valves.  Pressurise heating system to 4 bar pressure (60psi) bleeding off residual air from air vents on the manifold top.  Check visually all heating circuits and manifold connections for leaks. If, after 24 hours pressure has not dropped screeding may commence.

UNDERFLOOR HEATING MUST REMAIN PRESSURISED WHILST SCREEDING


Continue...

Underfloor Heating 
How to Decide 
Engineering 
About Hilton Croft 

Search the site for:






















































 

Hilton Croft Ltd, Southern Counties House, 27-43 Ifield Road, Crawley, West Sussex, RH11 7AT
Tel: 01293 452657   Fax: 01293 426561